位于合肥經開區宿松路(lu)與觀海路(lu)交(jiao)口的智能科技園六期(qi)南地塊項目,歷(li)經高效建(jian)設,目前已進入完工階段,驗收工作已全面啟動。
項目自開工(gong)(gong)(gong)以來(lai),依托 BIM技術及(ji) C-SMART數字化(hua)管理系(xi)統,實現施工(gong)(gong)(gong)全(quan)流程智能(neng)化(hua)管控,主體結構較(jiao)原計(ji)劃提前40天(tian)封(feng)頂,幕(mu)墻工(gong)(gong)(gong)程進度超前2個月。截(jie)至目前,施工(gong)(gong)(gong)已全(quan)部完成,項目進入驗(yan)收階(jie)段,施工(gong)(gong)(gong)團隊將加快(kuai)推進驗(yan)收工(gong)(gong)(gong)作(zuo),為項目的交(jiao)付保駕(jia)護航。
智(zhi)能科技園六(liu)期南地塊項(xiang)(xiang)目以“質(zhi)量+安全+創新”為核心,5棟單體建筑榮(rong)獲“合(he)肥市建筑工(gong)(gong)程優質(zhi)結構獎”,項(xiang)(xiang)目獲評“安徽省(sheng)安全文明(ming)標(biao)準化示范工(gong)(gong)地”榮(rong)譽(yu)稱號(hao),同時該項(xiang)(xiang)目申報的(de)“安心工(gong)(gong)地”、“紅色工(gong)(gong)地”、“智(zhi)慧(hui)工(gong)(gong)地”、“綠色工(gong)(gong)地” 四個工(gong)(gong)地試點通過合(he)肥市主管部門審批(pi)。
下一步,項目全(quan)面竣工后將啟動企(qi)業入駐籌備。這座集“產(chan)、研(yan)、創(chuang)”于一體的現(xian)代(dai)化科技園區正(zheng)在從(cong)藍圖變為(wei)現(xian)實,將成(cheng)為(wei)合(he)肥市科技創(chuang)新和產(chan)業升級的重(zhong)要推動力。(經開(kai)建(jian)投公司)